Project Planning — PE WRE

Topic video on its way — a detailed walkthrough of Project Planning, with animations and worked examples.

Watch the topic: the detailed video walkthrough of Project Planning will sit here.

Take the 3-question mini-quiz ↓

Quantity take-off and cost estimating

A quantity take-off measures the work from the drawings — lengths, areas, volumes — before any price is attached. Estimates then apply unit prices that carry labour, material, equipment and overhead. Keep the estimate class honest: a planning-level estimate is a range, not a promise, and contingency exists because quantities and prices both move. On the exam, take-off questions are pure geometry plus one adjustment such as swell, waste or a stated contingency.

Volume = length × width × depth  ·  Estimate = Σ (quantity × unit price), then add contingency

Worked example Trench excavation take-off

Given: A sewer trench is 200 ft long, 4 ft wide and 6 ft deep. Find the excavation volume in cubic yards.

Solution:

  1. Volume = 200 × 4 × 6 = 4,800 ft³.
  2. Convert: 4,800 / 27 = 177.8 yd³.
  3. No swell or waste factor is stated, so none is applied.

Answer: Excavation ≈ 178 yd³.

Project schedules and the critical path

In a precedence network, the critical path is the longest chain of dependent activities; it sets the project duration, and every activity on it has zero float. Float is the amount an activity can slip before it delays the finish: total float = late start − early start. Exam questions give a small network and ask for the duration, the critical path, or the float on one activity — work forwards for early times, then backwards for late times.

Project duration = longest path length  ·  Total float = LS − ES = LF − EF

Worked example Critical path and float

Given: Activity A (3 days) starts the project. B (4 days) and C (2 days) both follow A. D (3 days) follows both B and C. Find the project duration and the float on path A–C–D.

Solution:

  1. Path A–B–D: 3 + 4 + 3 = 10 days.
  2. Path A–C–D: 3 + 2 + 3 = 8 days.
  3. The longer path governs: duration = 10 days, so A–C–D carries 10 − 8 = 2 days of float.

Answer: Duration = 10 days; the A–C–D path has 2 days of float.

Economic analysis: present worth and lifecycle cost

Money has a time value, so alternatives are compared only after every cost is moved to the same point in time. Present worth discounts a future sum with P = F/(1 + i)n; lifecycle cost adds first cost, discounted operating and maintenance costs, and any discounted salvage (subtracted). The lowest present-worth lifecycle cost wins — not the lowest first cost. Watch the sign of salvage and the direction of the discounting.

P = F / (1 + i)n  ·  (A/P, i, n) = i(1 + i)n / [(1 + i)n − 1]

Worked example Present worth of a future cost

Given: A pump station needs a $10,000 overhaul in 10 years. At i = 5%, what is its present worth?

Solution:

  1. (1.05)10 = 1.6289.
  2. P = 10,000 / 1.6289 = $6,139.
  3. The present worth is less than the future sum — discounting always shrinks a future cost at a positive rate.

Answer: Present worth ≈ $6,139.

3-question mini-quiz

Project Planning

Choose your answer, then check it to see the result and explanation.

1. A capital cost of $100,000 is recovered over 20 years at 5%. Using (A/P, 5%, 20) = 0.0802, the equivalent uniform annual cost is closest to:

2. In a schedule network, an activity on the critical path has total float of:

3. A rectangular excavation is 100 ft long, 10 ft wide and 5 ft deep. Its volume is:

Ready for the complete rehearsal?

Step up from this three-question taster to the full timed PE WRE simulation — 80 questions in exam conditions, with a per-area diagnostic.

Keep building exam speed

This whole hub is free — every area page, mini-quiz and podcast. When you are ready to rehearse under exam conditions, the separate PE WRE exam simulation runs the full 80 questions against the clock.

Preview the PE WRE exam simulation Open the exam simulator