Quantity take-off and cost estimating
A quantity take-off measures the work from the drawings — lengths, areas, volumes — before any price is attached. Estimates then apply unit prices that carry labour, material, equipment and overhead. Keep the estimate class honest: a planning-level estimate is a range, not a promise, and contingency exists because quantities and prices both move. On the exam, take-off questions are pure geometry plus one adjustment such as swell, waste or a stated contingency.
Volume = length × width × depth · Estimate = Σ (quantity × unit price), then add contingency
Worked example Trench excavation take-off
Given: A sewer trench is 200 ft long, 4 ft wide and 6 ft deep. Find the excavation volume in cubic yards.
Solution:
- Volume = 200 × 4 × 6 = 4,800 ft³.
- Convert: 4,800 / 27 = 177.8 yd³.
- No swell or waste factor is stated, so none is applied.
Answer: Excavation ≈ 178 yd³.
Project schedules and the critical path
In a precedence network, the critical path is the longest chain of dependent activities; it sets the project duration, and every activity on it has zero float. Float is the amount an activity can slip before it delays the finish: total float = late start − early start. Exam questions give a small network and ask for the duration, the critical path, or the float on one activity — work forwards for early times, then backwards for late times.
Project duration = longest path length · Total float = LS − ES = LF − EF
Worked example Critical path and float
Given: Activity A (3 days) starts the project. B (4 days) and C (2 days) both follow A. D (3 days) follows both B and C. Find the project duration and the float on path A–C–D.
Solution:
- Path A–B–D: 3 + 4 + 3 = 10 days.
- Path A–C–D: 3 + 2 + 3 = 8 days.
- The longer path governs: duration = 10 days, so A–C–D carries 10 − 8 = 2 days of float.
Answer: Duration = 10 days; the A–C–D path has 2 days of float.
Economic analysis: present worth and lifecycle cost
Money has a time value, so alternatives are compared only after every cost is moved to the same point in time. Present worth discounts a future sum with P = F/(1 + i)n; lifecycle cost adds first cost, discounted operating and maintenance costs, and any discounted salvage (subtracted). The lowest present-worth lifecycle cost wins — not the lowest first cost. Watch the sign of salvage and the direction of the discounting.
P = F / (1 + i)n · (A/P, i, n) = i(1 + i)n / [(1 + i)n − 1]
Worked example Present worth of a future cost
Given: A pump station needs a $10,000 overhaul in 10 years. At i = 5%, what is its present worth?
Solution:
- (1.05)10 = 1.6289.
- P = 10,000 / 1.6289 = $6,139.
- The present worth is less than the future sum — discounting always shrinks a future cost at a positive rate.
Answer: Present worth ≈ $6,139.